Documents vs. Tasks in Pilot 1

D
O
C
U
M
E
N
T
S

T3

TASKS    1      2     3

Description Type Origin Amended Used T3 T3-1 T3-2 T3-3 T3-4 T3-5
 
D-4 EU test report Text 2.7.2 2.7.1 3.0 .          
D-5 DC Test report Text 2.7.2   3.0 .          
D-6 Joint test report Text+CAD 2.7.3   3.0 .          
 
E-3 Project specs Text+Drawings EU   3.2     .      
E-4 General Conditions Text EU   3.2     .      
E-5 Analog Drawings EU   3.2     .      
 
D-7 Scanned Drawings TIF + text 3.2.2 3.2.1 3.3.1       .    
D-7A Commented Scans Tif + Annot 3.2.2 3.2.1 3.3.1       .    
D-7U/F Revised Scanned Test Drawings Until Final Tif + text + annot 3.2.1 3.2.2 3.3.1       .    
 
D-8-1 CAD production stage 1 CAD + text 3.3.2 3.3.1 3.4         .  
D-8-1A Commented CAD production stage 1 CAD + text 3.3.2 3.3.1 3.4         .  
D-8-1U/F Updated CAD production stage 1 until final CAD + text 3.3.1 3.3.2 3.4         .  
 
D-8-2 CAD production stage 2 CAD + text 3.3.2 3.3.1 3.4         .  
Etc. Etc. Etc. Etc. Etc. Etc.            
D-9 Adjusted CAD files for internal use Native CAD 3.4   3.5           .

A typical description for a document to go here.